1Summary
The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026, S.I. 2026/1192, come into force on 08 December 2026. They amend the 2012 England planning-fee regulations, replacing the development fee table and changing charges for other applications, requests and site visits. The instrument protects applications made before commencement and specified enforcement cases. Matthew Pennycook made it for the Secretary of State for Housing, Communities and Local Government on 10 November 2026. Its free-issue notice concerns copies of the instrument, not a waiver of planning fees.
2What changes
- Regulation 3 changes fees for certificates of lawful use or development, including the dwellinghouse scale and its thresholds. The instrument substitutes £360 for the stated £293 fee and £700 for £578 in the specified provisions; larger housing cases use new per-dwelling rates and a cap.
- Regulation 4 changes fees for applications under the General Permitted Development Order, removes specified sub-paragraphs and adds a £310 fee for other applications under the relevant Schedule. This introduces a charge for certain prior-approval applications that previously attracted no fee. The regulation also revises the housing-related scale and makes one existing charge subject to another provision.
- Regulations 5 to 8 change mining and landfill monitoring, condition-compliance confirmation, non-material change and appropriate alternative development certificate fees. The instrument substitutes £125 for £86 for the specified householder condition-compliance request and £964 for £293 for the alternative development certificate.
- Regulation 9 changes the amounts covered by annual indexation under regulation 18A of the 2012 Regulations. It adds the new prior-approval and permission-in-principle fees and Schedule 1 paragraph 14(2), which concerns outline applications spanning more than one development category.
- Regulation 10 changes individual Schedule 1 charges, introduces an £825 flat fee for permission in principle and replaces the development scale. The replacement covers operations and uses of land, including housing, other buildings, agricultural development, minerals and changes of use. Regulation 11 changes the Schedule 2 advertisement fees.
- The substituted monetary amounts in the instrument are amendments to figures written in the 2012 Regulations. Existing annual indexation means those figures should not automatically be treated as the fees payable immediately before 08 December 2026.
- Regulation 12 disapplies regulations 3 to 11 to applications made before 08 December 2026; applications deemed made under section 177(5) of the Town and Country Planning Act 1990 in connection with an enforcement notice issued before that date; requests made before that date; and site visits taking place before that date. The enforcement exception turns on the notice date, not simply the deemed-application date.
- For amended amounts, regulation 12 substitutes 01 April 2027 as the first fee-change date under regulation 18A. That regulation increases relevant amounts when the preceding September consumer prices index exceeds the previous September’s, by the lower of that increase and the applicable cap, rounded to the nearest pound. Its increase applies to applications made or deemed made on or after the fee-change date.
- The instrument says it corrects an error in S.I. 2023/1197 but its free-issue notice does not identify it. The notice does not expressly identify the error.
3Who is affected
Applicants for affected planning permissions, certificates, prior approvals, condition confirmations and other services pay the applicable charges. Local planning authorities collect the fees and may receive more income, depending on application volumes and the allocation of receipts. Applicants within the transitional exceptions remain subject to the earlier rules for those cases.
The regulations extend to England and Wales but amend the fee regime for England; legal extent does not itself make the England fees applicable to Welsh applications. In its consultation response, the department says the national schedule aims at an estimated share of processing costs. That is an estimate, not a requirement that each authority recover that proportion or evidence that decisions will be faster.
4Key dates
- 10 November 2026: The minister made the regulations for the Secretary of State.
- 08 December 2026: The regulations come into force; the transitional exceptions distinguish earlier applications, requests, enforcement notices and site visits.
- 01 April 2027: First fee-change date for the amended amounts under the regulation 18A indexation mechanism.